The total earthworks (excavating, transportation, unloading and filling/compacting) was over 56.926 million cubic meters.

  • More than 130 heavy equipment vehicles and machinery were employed such as dump trucks, water trucks, cement trucks, bulldozers, graders, trenchers, scrapers, backhoes, excavators, cranes, etc. 
  • 44 mine pits and quarries were cleaned, drained and filled in.
  • 35 water reservoirs, both large and small were built. 
  • The total earthworks (excavating, transportation, unloading and filling/compacting) was over 56.926 million cubic meters. That’s equivalent to…
    • 25 of the Great Pyramids of Giza
    • nearly half of the earthwork of the Three Gorges Project in China
    • 900 Spaceship Earths from EPCOT
    • 5 million cement trucks
  • Total project investment of ¥5.16B RMB ($728.46M USD)